Irrigation & Re-Grassing Project Update
We have made great progress on the project the past five weeks. The weather has cooperated for the most part and we are a week away from starting to sod and sprig new grass on phase 1 holes.
Below is a list of our progress on the project:
BOMAG (rototill): holes 1-18 and the practice range
Drainage pipes: 3100 LF (linear feet) out of 4100 LF completed
New pump station and wet well installed
Rough shaping: holes 6-12
Irrigation installed: holes 9, 10, 11 and half of 12
Finishing shaping: 11, holes 9, 10, 12 to be finished later this week
Grassing on holes 8-12 are tentatively scheduled for the week of May 15